Customer pain points

Low cargo handling efficiency

High cargo damage rate

Low warehouse space utilization

High labor costs

Implementation plan

Warehouse information: about 3224㎡

Total number of cargo spaces: 15337

Number of equipment: 26 four-way vehicles, 7 elevators

Project value

Intelligent management improves cargo handling efficiency, increases warehouse space utilization, and reduces cargo damage rate

During off-peak hours, the inbound efficiency is 57 pallets/hour, and the outbound efficiency is 82 pallets/hour; during peak hours, the inbound efficiency is 92 pallets/hour, and the outbound efficiency is 129 pallets/hour.